19Sep2010 14Z Daily GRIP Telecon

GRIP Banner

19Sep2010 14Z Daily GRIP Telecon

Flight Date: 
Sun, 09/19/2010

19 Sep 2010

GRIP (FLL-JSC-DFRC) 14Z Daily Telecon / Webinar

Participants

FLL Team –Marilyn Vasquez, Ed Zipser, Cerese Albers, Michele Garrett, Instrument and Forecast teams

Telecon : Bjorn Lambrigtsen, Rich Blakeslee, Michael Goodman, Scott Braun, Gerry Heymsfield, Bud Mein

Global Hawk Report

  • Aircraft – green 
    • No fly day
    • NCAR Droposonde team team to arrive today

ATC Radio is repaired 

 

  • Droposonde – red

Dropsonde people returning to DFRC on Sunday and hope to perform vibration and ground test on Monday.  Fly test flights on Wednesday.

Re-fly of Low Altitude test flight and high altitude flights in one day. Must be a weekday and have a chase plane.

  • HAMSR – green.
  • LIP - green
  • HIWRAP – yellow
    • Some noise in 2-channels in the Ka band
    • Analyzing data

 

WB-57 Report

  • Aircraft - green
  • HIRAD – green
    • HIRAD removed from NASA926– but this is standard procedure since no targets in range. N926 to be used this week for pilot procedure
  • WB-57 approved to extend flights until at least 30September
  • Science team headed back to HSV waiting for storms to approach
  • NAST-I still delayed – probably will not take part.

DC8 Report

  • Aircraft– green.
    • Today is a No Fly Day
    • Alert in the system for a suitecase to STX – decision to be made at 16Z telecon (based upon outlook – this is unlikely for Monday)
    • Nothing promising on the horizon in the Caribbean
  • LASE – green.
  • LARGE – green.
  • APR2 – green.
  • DAWN – green.  
  • Microphysics – green
    • CSI cannot fly for the duration of GRIP
  • MMS – green.
  • Dropsonde – green. 

Science

  • Work has begun on preparation of charts for NASA HQ briefing.
  • Need platform scientist reports for GH
  • This week consider flying intense localized systems – non-tropical cyclone but good convective events.  Test the GH in these convective systems with lightning
  • Tuesday is the last possible day to suitcase to STX
  • Not considering flying a one-shot into a single storm
  • Thursday-Friday would be the last two flight days if a storm is flyable.  This decision would be made on Wednesday
  • DC8 in Atlantic: If no Genesis or Rapid Intensification then look for Dust – possibly a 4-5 hr mission to satisfy LASE, LARGE and DAWN
  • GH extension for LIP, HAMSR, HIWRAP?  - If nothing on the horizon on 24Sep then these instruments may end their participation in the experiment
Attachment Size
GRIP telecon 14z_19Sep2010.docx 17.16 KB

 