Update for Monday's mission planning

MC3E banner

Update for Monday's mission planning

Date: 
Sun, 05/22/2011

The 12Z and 18Z model runs are consistently putting precipitation into the CF area earlier that what we gathered from the 06Z run.  Accordingly we now estimate the t/o time for the ER-2 to be 21Z Monday (full mission) and 2330Z Monday  for the UND (full mission).  We will meet tonight at 10 PM local to look at the 00Z runs and communicate a ER-2 (firm) t/o time shortly after that brief meeting.  We will update UND at tomorrow's 9 AM briefing.  

 

We hear that the N-pol staff are making good progress in resolving the problem at N-pol.  They have all put in a long day of hard work trying to resolve the problem.  We are hopeful they will be up and running for Monday's night event.  Thanks guys!

Rutledge/Nesbitt/Pavlos

 